The Initial Sample Inspection Report (ISIR)—in German-speaking regions known as the EMPB—is a standardized document in the automotive industry that summarizes all results of the initial sampling of a new or modified part. It includes dimensional measurements, material proofs, functional tests, and process parameters. As Element 13 of the PPAP, it is the central evidence that a component meets all design and quality requirements before mass production begins.
While international markets often follow AIAG PPAP standards, German OEMs primarily operate according to VDA Volume 2 (Quality Assurance for Supplies).
An inspection report is mandatory not only for the first-ever launch of a part but also for specific change classes defined by VDA 2 or Customer Specific Requirements (CSR):
A complete report is divided into several sections:
Rejections often stem from the same recurring issues:
A digital process connects the characteristic list from the CAD drawing directly to the measurement data acquisition:
What is the difference between an ISIR and a PSW?
The ISIR/EMPB is the technical test document containing all measurement results. The PSW (Part Submission Warrant) is the summary cover sheet and the supplier's formal declaration that the entire PPAP (including the ISIR) is complete and compliant. The ISIR is a component of the PPAP; the PSW is the conclusion.
Can an ISIR be submitted with negative results?
Yes, but only with a documented Deviation/Waiver approved by the customer. If a feature is out of tolerance, the supplier must prove that corrective actions are initiated or obtain a formal temporary approval. An ISIR with failures and no waiver will be rejected immediately.
How long must ISIR documents be archived?
At least for the duration of series production plus the years defined by the customer—typically 15 to 25 years for safety-critical components (as vehicles may remain in use for decades).
How many samples are required?
VDA Volume 2 recommends at least 5 samples per cavity or tool. For multi-cavity tools, every cavity must be measured separately. Always check your specific CSR for the exact count.
MES software compared: vendors, functions per VDI 5600, costs (cloud vs. on-premise) and implementation. Honest market overview 2026.
OEE software captures availability, performance & quality automatically in real time. Vendor comparison, costs & case studies. 30-day free trial.
MES (Manufacturing Execution System): Functions per VDI 5600, architectures, costs and real-world results. With implementation data from 15,000+ machines.