Enter demand and lead time
Use daily figures on one time basis. Include approval, transport and goods receipt in replenishment lead time.
Each scenario changes one input. The second applies in statistical mode. The reorder point is rounded up for whole parts.
Check demand and lead time per item. Trigger replenishment from inventory position: available stock plus open receipts minus backorders. Compare the buffer with actual stockouts regularly.
Use daily figures on one time basis. Include approval, transport and goods receipt in replenishment lead time.
Enter known safety stock. For the statistical approximation, also enter the standard deviation of daily demand and cycle service level.
The reorder point is rounded up to whole parts. The breakdown separates expected demand from the extra buffer.
d × L + SSDaily demand d, lead time L and safety stock SS.
SS = z × σd × √LIndependent daily demand and constant lead time; z is the standard normal quantile.
Reorder point ÷ dZero daily demand has no finite stock coverage.
At 100 parts per day, a 10-day lead time and 200 parts of safety stock, the reorder point is 1,200 parts.
| Item | Calculation | Result |
|---|---|---|
| Lead-time demand | 100 × 10 | 1,000 parts |
| Buffer | Direct input | 200 parts |
| Reorder point | 1,000 + 200 | 1,200 parts |
| Coverage | 1,200 ÷ 100 | 12 days |
Multiply average daily demand by replenishment lead time and add safety stock. Round up for whole parts.
For constant lead time, the approximation is z × standard deviation of daily demand × square root of lead time. You can also enter a known buffer directly.
The one-sided quantile is approximately 1.644854. The calculator uses the stored value without rounding it to two decimals.
Reorder point triggers replenishment. Safety stock is the extra buffer during replenishment.
The rounded reorder point divided by average daily demand. This is a calculated duration at constant demand.
A free tool by SYMESTIC, a cloud Manufacturing Execution System.