1
Shift and downtime data – the basis for Availability.
Total shift time
min
e.g. 480 = 8 hours
Planned downtime
Breaks, shift changes, planned maintenance
min
!
=Planned production time
420min
Unplanned downtime
Breakdowns, changeovers, missing material
min
!
=Operating time
345min
Calendar time
1440 = 24 h (1 day) – same basis as the shift above
min
!
2
Part counts and cycle time – the basis for Performance and Quality.
Ideal cycle time
Theoretically fastest time per unit
!
Total parts produced
pcs
Good parts + scrap + rework
Scrap
pcs
!
Rework
pcs
=Good parts
550pcs
=Theoretically possible parts
690pcs
3
Add the margin per unit to see your loss in €.
Contribution margin per unit
EUR
Margin / lost profit per good part
Currency
Shifts per day
Production days / year
4
Select your industry for the benchmark comparison.
Industry
OEE
Target 85 %
Rating
TEEP
Utilization
!
Performance above 100 % – please check the cycle time, part count or operating time. The ideal cycle time is probably set too optimistically.
Availability
Target 90 %
Performance
Target 95 %
Quality
Target 99.9 %
Breakdown of planned production time into effective production and losses.
Total loss
0 %
of planned production time
100 %
Effective production (OEE)
Availability loss
Performance loss
Quality loss
€
Hidden Factory – your €-potential
Enter a contribution margin per unit on the left to calculate your hidden potential in euros.
The six big loss categories, mapped to the three OEE factors.
Availability
Equipment breakdowns
Setup & changeover losses
Performance
Idling & minor stops
Reduced speed
Quality
Quality defects / scrap
Startup & rework losses
A more precise breakdown by individual cause comes from a Reason-Code-Logger with live machine data.
Reason-Code-Logger
Your value
World-class target
85 %
World-class factors: Availability 90 % · Performance 95 % · Quality 99.9 %
Share & export your result
Your inputs are stored in the link – no account, no backend.
Please fill in the required fields on the left to see your OEE result.
A free tool from SYMESTIC – Manufacturing Execution System from the cloud.
GUIDE
How the OEE calculator works
OEE (Overall Equipment Effectiveness) measures how productively a machine actually runs. In four steps you get your value – including the breakdown into Availability, Performance and Quality as well as the resulting loss in euros.
1
Capture time data
Enter the total shift time as well as planned (breaks, maintenance) and unplanned downtime (breakdowns, changeovers).
2
Production & Quality
Enter the ideal cycle time, parts produced, scrap and rework – the basis for Performance and Quality.
3
Economics (optional)
Enter the contribution margin per unit to see the hidden loss in euros per shift and per year.
4
Read your result
Your OEE value, the three factors, the biggest lever and the benchmark against the world-class target of 85 %.
The OEE formula
OEE
=
Availability
×
Performance
×
Quality
Availability
Operating time ÷ planned production time
World-class target: 90 %
Performance
(ideal cycle time × parts produced) ÷ operating time
World-class target: 95 %
Quality
Good parts ÷ parts produced
World-class target: 99.9 %
FAQ