FMEA: Excel template

Use this template to rate potential failures for each process step by severity, occurrence and detection and track every action until it is re-rated.

Download the template

FMEA Template for Excel with RPN

What is in the template

Excel calculates the risk priority number from S, O and D. You determine the action priority from the table in the AIAG-VDA handbook and select it from the list.

  • Process FMEA with header for plant, process, team, date and revision
  • Columns from process step and failure mode to detection controls, based on the AIAG-VDA FMEA handbook
  • RPN from S, O and D by formula, inputs from 1 to 10 validated, high values highlighted
  • Rating sheet with short descriptions of levels 1 to 10 for S, O and D
  • Actions with owner, due date, status and new rating
  • Filled-in example from a fictional assembly plant, Excel file without macros

Who it is for

Who the FMEA template is for

The template is for quality and process engineers who want to assess the risks of a manufacturing process before they turn into defects at the customer. Use it for new processes, after changes or to revise an existing process FMEA.

How to work with the FMEA template

  1. Structure the process

    Enter the process steps and describe failure mode, effect and cause for each step.

  2. Rate

    Score severity, occurrence and detection from 1 to 10. Excel calculates the RPN and highlights high values.

  3. Track actions

    Define actions with owner and due date and re-rate after implementation.

What you should know about FMEA

  • RPN and action priority rate differently

    The RPN multiplies S, O and D and weights all three equally. The action priority from the AIAG-VDA handbook puts severity first, which is why the template includes both.

  • Detection does not replace prevention

    A better inspection lowers the detection rating, but the cause remains. Actions that lower occurrence act earlier and more reliably.

  • An FMEA is never finished

    After a complaint, a process change or a new finding, the FMEA goes back on the table. The columns for the new rating show whether an action has reduced the risk.

How to

How to fill in a process FMEA in Excel

A process FMEA lists every process step, asks how it can fail and rates each failure by severity, occurrence and detection on scales from 1 to 10. In Excel, one row holds one chain of failure mode, effect and cause. The risk priority number is RPN = severity × occurrence × detection, with values from 1 to 1,000.

Work through the columns in order. Process step and function come from the process flow chart. The failure mode describes how the step misses its function, for example torque too low. The effect describes what the next process, the customer or the end user notices. The cause names what triggers the failure mode. Prevention controls lower occurrence, detection controls find the failure before the part moves on. Rate only when these columns are complete, and rate as a team.

Since the AIAG-VDA FMEA handbook of 2019, the action priority high, medium or low replaces the RPN as the basis for deciding on actions. The reason is that identical RPN values can hide very different risks: 8 × 3 × 4 and 4 × 6 × 4 both give 96, yet only the first involves a severe effect. A fixed RPN threshold such as 100 misses severe failures with low numbers.

Example

Example: Process FMEA rows for a screw joint station

Three failure modes at an assembly station, one of them rated again after an action. All ratings are example values.

Failure modeSODRPN
Missing weld nut83496
Torque too low746168
Scratch on visible surface46372
Torque too low, after torque monitoring74256

Torque monitoring cuts the RPN from 168 to 56 through better detection, while occurrence stays at 4. The missing weld nut ranks below the torque failure by RPN, but with a severity of 8 it is the first candidate for an action when you rank by severity.

Questions and answers

Common questions about the FMEA template

  • What is the difference between a DFMEA and a PFMEA?

    A design FMEA looks at how the product can fail because of its design, for example a wall that is too thin. A process FMEA looks at how manufacturing and assembly can produce a defect, for example a missing or loose screw. The severity ratings from the DFMEA feed into the PFMEA for the same effects.

  • How do you rate severity, occurrence and detection?

    Use one rating table for the whole company, such as the tables in the AIAG-VDA handbook. Severity rates the effect, occurrence rates how likely the cause is with the current prevention controls, and detection rates how well the current controls find the failure. The team agrees on each value and notes the reason.

  • What is action priority in FMEA?

    Action priority is a table in the AIAG-VDA handbook that assigns high, medium or low to every combination of severity, occurrence and detection. Severity carries the most weight. High means the team must define an action or document why none is needed, medium means it should, and low means it could.

  • How is the FMEA linked to the control plan?

    The process FMEA shows which characteristics carry a risk and which detection controls the team relies on. The control plan turns these controls into inspections in series production, with method, frequency and reaction. When the FMEA changes, check whether the control plan has to change as well, and the other way round.

Download the FMEA template